The Jovi ERP production module is the layer that schedules the order pool against capacity and follows a work order down to the shop floor. Master production scheduling (MPS), material requirements planning (MRP), the bill of materials, capacity planning and real-time tracking all run on the same data, and quality checks hang off the same work order.

WO-2417 · LINE 3 running
  • Sheet cutting CNC-04 68%
  • Welding ROB-02 31% stopped · awaiting material
  • Assembly ASM-A1 0%
  • Final check QC-1 0%
74 OEE
Planned finish 14:20
Shift 2 / 3
A single work order across the four operations on its routing. Welding has stopped waiting on material; the order stays open, because the stoppage belongs to the station and not to the order. Representative interface.
Productivity gain
35%
Cost reduction
28%
Fewer defects
45%
Faster planning
50%

The Jovi ERP production module digitises production operations and removes the manual steps in between. From work order to quality control, from capacity planning to performance analysis, everything runs on one platform. Real-time data means decisions happen now and bottlenecks surface early.

The same flow works for a single workshop and a multi-line plant: recipes and capacity are defined, MRP computes the requirement, the work order reaches the floor, floor data comes back, and the plan updates itself.

Use case

A furniture maker producing sixty SKUs runs its daily order flow through Jovi ERP. The AI engine matches the order pool against capacity and due dates to build the daily sequence, and flags the line when balance slips.

What you can do

  • Planning and scheduling

    Build production plans automatically from capacity, material and labour availability. Plan visually with Gantt charts.

  • Work order management

    Create work orders, assign them to operations and track them live. Reprioritise and replan as the day changes.

  • Recipes and bill of materials

    Define multi-level BOMs and alternative recipes. Drive material requirements planning from them.

  • Capacity planning

    Define machine and work-centre capacity, surface bottlenecks and keep resources evenly loaded.

  • Real-time monitoring

    Collect shop-floor data as it happens, compute OEE and turn downtime analysis into improvements.

  • Quality control integration

    Define in-process control points, log non-conformities and produce quality reports.

Capabilities

Master production schedule

Build the master plan from forecasts and firm orders.

  • Demand forecast integration
  • Seasonal planning
  • What-if scenarios
  • Plan comparison

Material requirements planning

Calculate material needs automatically from the BOM.

  • Net requirement calculation
  • Lead-time management
  • Lot-size optimisation
  • Purchase suggestions

Shop-floor control

Watch and steer the floor in real time.

  • Barcode / RFID integration
  • Operator terminals
  • Machine connectivity (IoT)
  • Downtime tracking

Reporting and analysis

Analyse performance with full reports and dashboards.

  • OEE reports
  • Productivity analysis
  • Cost reports
  • Trend analysis
MRP · MPS-2026-W36 2 requests raised
  • MP-100 Chassis frame ×1 On hand 12 Committed 4 Net need
  • YM-210 Profile 40×40 ×4 On hand 180 Committed 60 Net need +60 PR-8841
  • YM-215 Bracket plate ×8 On hand 640 Committed 0 Net need
  • HM-330 Bolt M8 ×24 On hand 2,400 Committed 500 Net need +1,100 PR-8842
Requirements from the bill of materials, netted against stock on hand and what open orders have already claimed. The two materials that come up short become purchase requests — the two codes on the right are what the run produced.

What it changes

  • Up to 35% productivity gain across production
  • Lower scrap and rework rates
  • Better on-time delivery
  • Live visibility of real cost
  • Faster decisions on the floor
  • Higher adherence to the production plan

With AI

  • Optimal production sequence from the order pool and capacity
  • Early bottleneck detection
  • Scrap trend forecasting
  • Performance analysis per operator and machine

Typically deployed in

  • Automotive suppliers
  • Machinery
  • Metalworking
  • Plastic injection
  • Food production
  • Textile and apparel
  • Electronics
  • Furniture

Works with

This is where the software stops

The work order opens on a board, is read at a terminal, and runs on a machine. Jovi ERP does not drive the floor — it knows what the floor is doing and plans against it.

WO-2417 CUTTING TERMINAL WELDING DESPATCH LINE 3
Line 3 in elevation: the stations, the operator terminal and the overhead board.

Frequently asked questions

What exactly does the MRP in Jovi ERP do?

MRP works out material requirements from the bill of materials together with open work orders, stock on hand and lead times: what is needed, how much, and by when. Shortfalls become purchase requisitions. When the master production schedule changes, the requirement list is recalculated.

Is this factory automation software?

No. Jovi ERP is the production planning and tracking layer; it is not PLC, SCADA or machine control software. It does not drive machines — it plans what those machines will build, runs the work orders and tracks the result. It sits above your existing automation, on the planning side.

How does production connect to inventory and quality?

Opening a work order creates a material reservation in the inventory module, in-process checks land in the quality module, and finished output enters stock as semi-finished or finished goods. Because all three share one data model, cost, scrap and delivery date are read from the same record.